Edinburgh to pursue new delivery routes for Fountainbridge and Meadowbank homes
The council plans to keep both projects moving after developer partnerships ended, with the 1,169-home schemes still delayed.

Edinburgh’s council is changing how it will deliver its proposed Fountainbridge and Meadowbank housing projects after ending its arrangements with the selected developers. Together, the plans provide for 1,169 homes, including affordable housing, and both are behind schedule.
The council says it intends to take both developments forward. At Fountainbridge, the parties could not settle how development risks would be shared under standard terms. At Meadowbank, they failed to agree on costs. Both projects are recorded as delayed in the council’s 2026-27 housing capital-monitoring programme.
March 2030 is the latest projected completion date for each scheme. These dates are estimates, not a guarantee that the homes will be ready then. The change is to the way the projects are to be delivered; it does not indicate that any homes have been completed or offered to residents.
What is planned at each site?
Fountainbridge is planned as a mixed-use neighbourhood on a former brewery site next to the Union Canal. The masterplan approved in 2016 proposes 464 homes and 10,000 square metres of office space. The housing total includes 186 affordable homes: 115 for social rent and 71 for mid-market rent.
Cruden Homes and Buccleuch Property were chosen for Fountainbridge in 2021. Cruden withdrew from the development agreement when standard risk-sharing terms could not be agreed. The council is now advancing the project with a different supplier, a change that has delayed the scheme.
The Meadowbank proposal includes 705 homes around the rebuilt sports centre. Under its masterplan, 35% of the homes are intended to be affordable, most of them for social rent. The council is working with a contractor from its framework to build the affordable homes in the project’s first phase.
What happens next?
The Meadowbank arrangement with a consortium led by Graham, alongside Miller Homes and Panacea Property Development, ended by mutual agreement after the parties could not settle terms for the delivery stage. The council plans to use another supplier. It has not named new delivery partners for either development.
Both schemes were already running late. By September, £13 million of Fountainbridge spending planned for the budget was being shifted to later years as delivery arrangements changed. Meadowbank had £32.9 million budgeted for site remediation and affordable housing construction in 2026-27, but the parties had not agreed on costs.